Project Radar with Trendlines

Enter your project metrics to get a clear overview of your project's status.

The approved total budget for the project until completion.
The planned value of the work completed by the reporting date.
The actual value of the work completed by the reporting date.
The actual costs incurred for the work completed by the reporting date.
The estimated total cost of the project upon completion.
Schedule Variance.
Cost Variance.
Variance at Completion.

SPI: --

CPI: --

SV: --

CV: --

EAC: --

VAC: --

Conclusion

SPI Recommendation: --

CPI Recommendation: --

BAC (Budget at Completion): The total budget originally allocated for the project. It represents the expected total cost to complete the project.

PV (Planned Value): The planned value of the work that should be completed by a certain point in the project schedule. This value indicates how much the work should have cost up to this point.

EV (Earned Value): The value of the work actually completed by a certain point in time. EV helps measure the actual progress of the project.

AC (Actual Cost): The actual costs incurred for the work completed by a certain point in time. AC is used to monitor the cost-efficiency of project execution.

EAC (Estimate at Completion): The estimated total cost of the project upon completion. Recommendation: Regularly review cost forecasts and adjust budgets as needed.

SV (Schedule Variance): The difference between Earned Value (EV) and Planned Value (PV). A positive value indicates that the project is ahead of schedule, while a negative value indicates delays.

CV (Cost Variance): The difference between Earned Value (EV) and Actual Cost (AC). A positive CV indicates that the project is under budget, while a negative CV indicates a budget overrun.

VAC (Variance at Completion): The difference between Budget at Completion (BAC) and Estimate at Completion (EAC). This metric shows whether the project is expected to finish under or over budget.

SPI (Schedule Performance Index): The ratio of Earned Value (EV) to Planned Value (PV). An SPI of 1 or higher indicates that the project is on or ahead of schedule, while a value below 1 indicates delays.

CPI (Cost Performance Index): The ratio of Earned Value (EV) to Actual Cost (AC). A CPI of 1 or higher suggests that the project is within or under budget, while a value below 1 indicates a cost overrun.